Key takeaways

  • Give every bidder the same technical and logistical tender basis.
  • Require a system-specific method sequence with safety hold points.
  • Verify proposed personnel, competence evidence and escalation route.
  • Convert exclusions and inspection assumptions into priced, approved decisions.
  • Define report content, test evidence and close-out timing.
  • Score technical and delivery risk alongside price.

Make the tender basis comparable

Issue the same vessel particulars, maker and model, fault history, port window, access constraints and requested deliverables to every bidder. State whether the work is preventive maintenance, troubleshooting, commissioning support, calibration or a defined combination.

Ask bidders to return a line-by-line compliance schedule, not only a lump sum. A comparable tender identifies included hours, travel, attendance days, tools, test equipment, consumables, replacement parts and report preparation.

Read the method statement for sequence and control

The method should explain isolation, safe access, inspection, cleaning, component replacement, functional testing and restoration in an order suitable for the installed system. Generic statements such as “service as per OEM” do not show whether the bidder understands the actual filter, UV, chemistry, sampling or valve arrangement.

Look for hold points before energisation, chemical exposure or discharge, and for defined acceptance evidence. The method should state what happens when a pre-existing defect, unavailable utility or failed test prevents the planned sequence.

Test competence without accepting vague claims

Request the proposed personnel, relevant system training, role, availability and experience with the exact maker or equipment family. Confirm how supervision and technical escalation will work; a résumé listing general marine work is not proof of competence on a particular BWTS.

The tender should identify the proposed personnel, manufacturer-specific competence and escalation route without implying approval, certification or authority that the bidder cannot document.

Expose exclusions and assumptions

Build an exclusions matrix covering cranes, scaffolding, access, isolation, spare parts, calibration, shore power, chemicals, waste, class or authority attendance, travel delay and repeat visits. Ask bidders to price optional lines where the vessel can reasonably define them.

Treat “subject to inspection” as a commercial and technical risk requiring a decision rule. The tender should state how discovered work is documented, who approves it, how rates apply and whether the vessel can stop without paying for unapproved extras.

Compare deliverables and close-out quality

Require a dated service report identifying equipment tags, as-found condition, work performed, parts and serial numbers, test conditions, alarms, limitations and recommendations. If calibration is included, specify certificate identification, result and due-date information rather than accepting “calibration completed.”

Set a close-out deadline and document format, including photographs or data exports where needed. A technically sound visit that leaves no reproducible evidence creates avoidable work for the ship and weakens future troubleshooting.

Score risk as well as price

Use weighted criteria for technical conformity, method quality, personnel, availability, exclusions, evidence, response time and total cost. Record reasons for scores and distinguish a missing tender response from a technically unacceptable proposal.

Before award, resolve deviations in writing and attach the accepted scope, method, rates and deliverables to the order. A tender evaluation is a procurement decision, not an independent certification of the BWTS.

Frequently asked questions

Is the lowest BWTS tender normally the best value?

No. Missing tests, travel, tools, parts or documentation can move cost and risk back to the vessel. Compare complete scope and exclusions before comparing totals.

What should a method statement include?

It should cover isolation, access, work sequence, hazards, hold points, testing, restoration and the response to discovered defects or unavailable utilities.

What should a tender say about maker-specific competence?

It should identify the proposed personnel, relevant system experience, documented competence and escalation route without implying approval, certification or authority that cannot be substantiated.

Should calibration be a separate tender line?

Usually yes, because it clarifies instruments, standards, certificates, results and due dates and prevents a vague service phrase from hiding an incomplete deliverable.

Sources

Related articles

Request spares, calibration or ballast-water testing

Include BWMS brand/model, vessel/IMO number, port/terminal, date/ETA and scope or part numbers. These links prepare an email draft; you must send it yourself.

  • Request a parts quote — Sensors, TRO reagents, calibration kits and replacement parts. Confirm compatibility, availability and delivery for your installed system.
  • Request a calibration booking — Annual instrument calibration with a calibration certificate for the work completed. OEM instructions, drift or applicable rules may require earlier work.
  • Request testing coordination — Arrange sampling and testing with an appropriately qualified party for your IMO D-2, commissioning or other stated purpose.

Authorised Headway agent. Other-brand enquiries are independently reviewed; no OEM authorisation is claimed. Sea Clean is not an accredited laboratory or approving authority. Calibration does not demonstrate biological D-2 compliance. Attendance, testing scope and parts delivery are confirmed per enquiry.